Phase II | WHERE WE'RE BUILDING FIBER NOW!

2:13PM June 11, 2020




Cherokee County


Southridge Tahlequah - Mainline construction & splicing is complete and we are building service drops and connecting homes NOW!  Give us a call 918-772-2526 if you live in Southridge and ready to experience a better internet, TV, or home phone service connection. 

QUA1 - Burnt Cabin & Tenkiller Habor - Mainline construction is complete, mainline splicing is underway. This zone is large and rural but we are stepping up to the plate and providing real internet in these areas.  If you live in this area and are interested please pre-register for a service drop today, this will speed up the construction process. We are hoping to start connecting homes inside this zone in July 2020. 

PEG1 -  Lost City -  Mainline construction has started!  Please be sure you are pre-registered while crews are working in this zone. Our goal is to start connecting homes in November 2020.

LOW2 - Lowery School - onsite engineering crews are driving out this section of the line. Then engineering will design the construction maps and we will move crews into this zone for construction late summer 2020.


Wagoner County


WAS1 - Taylors Ferry - Mainline construction has started. Our goal is to start connecting homes in this zone by November 2020. 

WAS3 - Bakers - Mainline construction has started. Our goal is to start connecting homes in this zone by November 2020. 

WAS4 - Mallard Bay - Mainline construction has started. Our goal is to start connecting homes in this zone by November 2020.

COW3 - Porter - Engineering and design. Our goal is to start connecting homes in this zone by the end of the 2020 year. 

COW2 - Osage Mound -  Engineering and design. Our goal is to start connecting homes in this zone by the end of the 2020 year.


Muskogee County 


GRE2 - Greenleaf Park -  Engineering and design. Our goal is to start connecting homes in this zone by the end of the 2020 year. 

GRE1 - Camp Gruber -  Engineering and design. Our goal is to start connecting homes in this zone by the end of the 2020 year. 