Phase II | Fiber Construction Update | 6/15/21
10:49AM June 15, 2021
Due to weather conductions (lots of rain) and fiber construction material supply delays, we have pushed back our expected home install starting dates in several of our construction zones.
All in-service zones on the fiber map (green)
- If a home or business needs a new fiber drop built, staking and construction can take 6-8 weeks.
- If your home or business already has a NID box outside, Lake Region will verify we have a light signal. You can expect an install appt. scheduled in 1 - 2 weeks. (if no outside construction is required)
New Zones
- Wagoner South (WAS1, WAS3, WAS4) –. installs are underway. Due to scheduling limits, we expect to continue with in-home installs for the next month for orders in the Wagoner South zone. As new service orders in Wagoner South come in, they are placed at the bottom of the list and can take several weeks.
- LOW2 – installs are underway! - We should have these last service lines in this zone completed by the end of June. – ready for in-home install by July.
- GRE1 & GRE2 - we expect to start home installs in August 2021.
- Jenkins (JKN1), we expect to start home installs in August 2021.
- Coweta (COW1, COW2, COW3) we expect to start home installs in August 2021.
- Livesay (LIV1) – we expect to start home installs in August 2021.
- Wagoner West (WAW1), we expect to start home installs in September 2021.
- Whitehorn (WHN3), we expect to start home installs in September 2021.
- Johnston (JHN1, JHN2) we expect to start home installs in September 2021.
Phase 3
- Phase 3 (remaining) Feeders on our electric system - mainline construction is expected to start this fall. Vantage Point is field data collecting for Phase 3 feeder now. We will break these zones/feeders out in phase 3 with a better ETA on when service installs will start once we launch into Phase 3.