Phase II | Fiber Construction Update | 5/5/21
9:48AM May 05, 2021
All in-service zones on the zone map (green)
· If the home or business needs a fiber drop built, staking and construction can take 6-8 weeks. (Crews have already finished this zone and moved on to the next zone)
· If the home or business already has a NID box installed - crews only need a light check. 1 -2 weeks.
A
New Zones - Active Construction (yellow)
2.1
·
Wagoner South (WAS1, WAS3, WAS4) – installs are
underway (started in April 2021). Could
still be several weeks of install appts needing set up (as light reading and QC’s
are finished).
·
LOW2 – the rest of the pending orders should be
called for install by end of May.
·
GRE1 & GRE2 – NO estimated time of service
available. Working through Easements, pole attachment agreement, and
tie-line design to light up Greenleaf POP building. We will update once we have
a better projection on when installs could start in GRE1 & GRE2.
2.2.1
·
Jenkins (JKN1) we expect to start installs in
June.
·
Coweta (COW1, COW2, COW3) we expect to start
installs in June.
·
Livesay (LIV1) – we expect to start installs in
June.
2.2.2
·
Wagoner West (WAW1) we expect to start installs
in July.
·
Whitehorn (WHN3) we expect to start installs in
July.
·
Johnston (JHN1, JHN2) we expect to start
installs in July.
Phase 3 (orange and gray)
· Phase 3 (remaining) Feeders on our system -
mainline construction is expected to start this fall. Vantage Point is field
data collecting for the design of Phase 2 now. We will break these zones/feeders out
in phase 3 with a better ETA on when service installs will start