11:39AM February 24, 2021
James Billinger
What the status on railroad permit for WAS area? My drop is almost complete and ready for install. WAS 3
9:23AM February 25, 2021
James Billinger
When will start WAS install? March or April?
8:27AM February 25, 2021
Lake Region Technology & Communications
We have received the permits, still have some mainline to complete before we have connectivity completed on your WAS fiber network. We are excited about completing this zone and getting our new customer up and running on the area's fastest network.
Processing..
Stand by, We are processing your payment. This window will close automatically.
Do not close your browser or press the back button.
11:39AM February 24, 2021
James Billinger
What the status on railroad permit for WAS area? My drop is almost complete and ready for install. WAS 3
9:23AM February 25, 2021
James Billinger
When will start WAS install? March or April?
8:27AM February 25, 2021
Lake Region Technology & Communications
We have received the permits, still have some mainline to complete before we have connectivity completed on your WAS fiber network. We are excited about completing this zone and getting our new customer up and running on the area's fastest network.